Renovation entering main phase

SUBJECT: PROGRESS OF MASTER PLAN WORKS

The work for renovation of the club building has entered its main phase. According to the time schedule, works will continue throughout July to August and it is expected they will be completed the last week of September. Unfortunately during this time we will suffer some inconvenience such as:

  1. Difficulty in the access from the parking side
  2. Unavailability of the men’s locker room.
  3. Unavailability men’s toilets. Temporarily women’s current toilets will be of common use.
  4. Closure of internal club spaces for certain days.
  5. Closure of part of exterior spaces for certain days.

 

We believe that these difficulties will be only slight more, because of their short duration but also due to the holiday season.